The Economics of the Olympics: Costs, Overruns and Who Pays

Every city that hosts the Olympics promises a well-run, affordable Games. The record says otherwise: according to the University of Oxford’s long-running study of Olympic costs, every Games since 1960 with available data has gone over budget. Here is where the money goes, who earns it, and who pays.

What the Games cost

Sports-related costs only, in 2022 U.S. dollars (Oxford Olympics Study 2024):

Summer GamesCostWinter GamesCost
Beijing 2008$8.3 billionSochi 2014$28.9 billion
London 2012$16.8 billionPyeongChang 2018$3.4 billion
Rio 2016$23.6 billionBeijing 2022$8.7 billion
Tokyo 2020$13.7 billion (official)
Paris 2024$8.7 billion

These figures leave out roads, rail, airports and hotels, which often cost more than the Games themselves. Tokyo’s official figure also excludes land and the city government’s own budget; adding them puts Tokyo at roughly $19–33 billion. The average Summer Games costs about $8 billion and the average Winter Games about $4 billion, and costs are rising over time.

Over budget, every time

  • 100% of Games with data had cost overruns.
  • The average overrun is 159% in real terms — the final bill is typically about 2.6 times the bid.
  • 18 of 23 Games overran by more than 50%; 13 of 23 by more than 100%.
GamesReal cost overrun
Montreal 1976720% — Montreal took three decades to pay off its Olympic debt
Rio 2016352%
Sochi 2014289%
Tokyo 2020128%
Paris 2024115% — from €3.6 billion in the bid to about €8.8 billion
London 201276%
Beijing 2008, PyeongChang 20182% (the smallest)

Even Los Angeles 2028, built around existing venues, has raised its forecast from $5.3 billion to $6.8 billion.

Where the income comes from

The International Olympic Committee sells the TV rights and global sponsorships. For 2021–2024 that was roughly $4.7 billion from broadcasting and about $3 billion from its worldwide (TOP) sponsors. The IOC says it redistributes about 90% of its revenue to the Olympic movement — including contributions to the host’s organizing committee, national Olympic committees and international sports federations.

The host’s organizing committee earns ticketing, local sponsorship and licensing revenue, plus its IOC contribution, and uses it to run the event. That is why organizing committees can “break even” while the Games as a whole cost far more: Paris 2024’s organizing committee finished with a surplus of about €75 million on €4.4 billion of spending — but venues, the athletes’ village, transport and security were largely paid for separately, mostly with public money.

Who benefits

  • The IOC, international federations and national Olympic committees — TV and sponsorship revenue.
  • Broadcasters and global sponsors — billions of viewers.
  • Construction firms — venues, villages and infrastructure.
  • Hotels, airlines and short-term rentals — though, as with the World Cup, regular tourists often stay away and the overall tourism gain is smaller than forecast.
  • Residents, sometimes — when the Games accelerate transport or housing that was needed anyway, as London’s regeneration of east London.

The biggest cost risk falls on taxpayers, because host governments usually guarantee to cover any shortfall.

The exception: Los Angeles 1984

After Montreal’s debts, Los Angeles was the only bidder for 1984. Voters had refused public funding, so organizers used existing venues and corporate sponsors — and finished with a $232.5 million surplus. Forty percent of it endowed the LA84 Foundation, which still funds youth sports in Southern California.

Why fewer cities want the Games

Cities including Hamburg (after a referendum in 2015) withdrew from the 2024 race, leaving only Paris and Los Angeles — so the IOC awarded 2024 and 2028 at the same time. The lesson from the numbers: cities that reuse existing venues and avoid open-ended public guarantees take far less risk.

Weigh promised benefits against costs yourself with the mega-event economic impact calculator.

Oxford figures are sports-related costs in 2022 U.S. dollars and real-terms overruns; organizers’ own accounts often report lower numbers.

Frequently asked questions

How much does it cost to host the Olympics?

According to the Oxford Olympics Study 2024, the average Summer Games costs about $8 billion and the average Winter Games about $4 billion in sports-related costs (2022 dollars), not counting roads, rail and airports. Rio 2016 cost $23.6 billion and Sochi 2014 $28.9 billion.

Do the Olympics always go over budget?

Yes, so far. Every Games since 1960 with available data overran its budget. The average overrun is 159% in real terms, and 13 of 23 Games more than doubled their budgets.

Do the Olympics make money?

The IOC does, mainly from about $4.7 billion of TV rights and $3 billion of global sponsorships per four-year cycle. Organizing committees often break even — Paris 2024’s had a surplus of about €75 million — but the full cost, including public spending on venues and infrastructure, is usually far higher than the revenue.

Which Olympics made a profit?

Los Angeles 1984 is the best-known example. Using existing venues and corporate sponsorship, it finished with a $232.5 million surplus, part of which endowed the LA84 Foundation.

Who benefits from hosting the Olympics?

The IOC and sports federations, broadcasters, sponsors, construction firms, and hotels and airlines during the Games. Taxpayers carry most of the financial risk because host governments usually guarantee any shortfall.

Sources